Project Documents and Updates
Let's ConnectLet's Connect Our Project Team is available to answer your questions.
Construction contractor or material vendor?
Submit this form.Investing in our future takes time, and we're committed to doing it right. We are undergoing a rigorous, multiyear federal and state permitting process, which includes extensive environmental reviews.
Project Updates
February 2, 2026
Basin Electric Power Cooperative has made the decision to exit the NTEC partnership. Basin Electric’s decision reflects their evolving business priorities and energy resource needs. ALLETE and Dairyland remain co-owners on the project and, as critical services providers, are currently evaluating next steps to meet growing energy demand. Natural gas is a flexible, reliable and low-cost resource to support the energy transition.
Neighborhood Meeting | Jan 23, 2024
Two neighborhood meetings were held on Tuesday, Jan. 23, 2024, at the Belgian Club. Meeting materials are available to view below.
Meeting Materials
December 15, 2023
Nemadji Trail Energy Center Receives Milestone Federal Approval
The RUS has, for the second time, issued a Finding of No Significant Impact (FONSI) for the Nemadji Trail Energy Center Project, which will aid reliability during the clean energy transition and bring family-supporting jobs to the city of Superior, Wis.
Read the Press Release FERC Waiver Application - August 9, 2023Environmental Reviews
Environmental Assessments (EA) and Environmental Impact Statements (EIS) are developed to determine whether or not an action (such as building a natural gas facility) is a “major federal action significantly affecting the quality of the human environment.” An EIS was completed by the Wisconsin Department of Natural Resources (DNR) and Wisconsin Public Service Commission in September 2019. The U.S. Department of Agriculture Rural Utilities Service (RUS) completed an EA of the Project in October 2020, a Supplemental EA in June 2022, and a Revised Supplemental EA in July 2023. The Final Supplemental Environmental Assessment was published in December 2023.
RUS Supplemental Finding of No Significant Impact - December 2023 RUS Notice of Supplemental Finding of No Significant Impact - December 2023 RUS Final Supplemental Environmental Assessment - December 2023
RUS Revised Supplemental Environmental Assessment - July 2023 RUS Supplemental Environmental Assessment - June 2022 RUS Environmental Assessment - October 2020 WI DNR Environmental Impact Statement - September 2019